ERP implementation schedule

An ERP implementation schedule template with process assessment, scope definition, configuration, integrations, data cleansing and migration, testing, training and hypercare. A practical baseline for aligning consultants, IT and business teams through go-live.

61 días hábiles12 tareas3 fases
Usar esta plantilla Gratis — abre en el editor listo para ajustar
SEM 1
SEM 2
SEM 3
SEM 4
SEM 5
SEM 6
SEM 7
SEM 8
SEM 9
SEM 10
SEM 11
SEM 12
SEM 13
Preparation
Kickoff and governance
Current process mapping
Scope and future process design
Configuration and data
Module configuration
Integration development
Data cleansing and preparation
Pilot data load
Validation and go-live
Integrated testing
Business acceptance
User training
Final migration and go-live
Hypercare
Vista previa del cronograma (semanas consecutivas a partir del inicio)
UNA PLANTILLA PARA TU TRABAJO

Convierte ERP implementation schedule en un proyecto real

Comienza con una estructura profesional y personaliza fechas, responsables y entregas en el editor. El cronograma recalcula las dependencias y queda listo para compartir.

  • Fases y tareas ya estructuradas
  • Plazos recalculados en días hábiles
  • Un solo enlace, siempre actualizado
Crear mi proyecto

Fases y tareas de la plantilla

1. Preparation

  • Kickoff and governance2 días hábiles
  • Current process mapping8 días hábiles
  • Scope and future process design6 días hábiles

2. Configuration and data

  • Module configuration15 días hábiles
  • Integration development12 días hábiles
  • Data cleansing and preparation10 días hábiles
  • Pilot data load4 días hábiles

3. Validation and go-live

  • Integrated testing8 días hábiles
  • Business acceptance6 días hábiles
  • User training5 días hábiles
  • Final migration and go-live2 días hábiles
  • Hypercare10 días hábiles