ERP implementation schedule

An ERP implementation schedule template with process assessment, scope definition, configuration, integrations, data cleansing and migration, testing, training and hypercare. A practical baseline for aligning consultants, IT and business teams through go-live.

61 business days12 tasks3 phases
Use this template Free — opens in the editor ready to adjust
WK 1
WK 2
WK 3
WK 4
WK 5
WK 6
WK 7
WK 8
WK 9
WK 10
WK 11
WK 12
WK 13
Preparation
Kickoff and governance
Current process mapping
Scope and future process design
Configuration and data
Module configuration
Integration development
Data cleansing and preparation
Pilot data load
Validation and go-live
Integrated testing
Business acceptance
User training
Final migration and go-live
Hypercare
Schedule preview (calendar weeks from the start)
A TEMPLATE FOR REAL WORK

Turn ERP implementation schedule into a real project

Start with a professional structure and customize dates, owners, and deliverables in the editor. The schedule recalculates dependencies and is ready to share with clients and your team.

  • Ready-made phases and tasks
  • Business-day dates recalculate
  • One link, always up to date
Create my project

Phases and tasks in this template

1. Preparation

  • Kickoff and governance2 business days
  • Current process mapping8 business days
  • Scope and future process design6 business days

2. Configuration and data

  • Module configuration15 business days
  • Integration development12 business days
  • Data cleansing and preparation10 business days
  • Pilot data load4 business days

3. Validation and go-live

  • Integrated testing8 business days
  • Business acceptance6 business days
  • User training5 business days
  • Final migration and go-live2 business days
  • Hypercare10 business days