Residential construction schedule template, from permit to handover

Use this template to plan a house build from the first set of drawings to the day the keys change hands. It covers 16 tasks across five phases (design and permits, foundation and structure, walls and roofing, building services and finishing) and adds up to 139 working days. Tasks are linked by dependencies, so a late slab pour or a failed inspection pushes every later date for you instead of leaving you to rebuild a spreadsheet.

139 business days16 tasks5 phases
Open the template, no sign-upSave to my account Free, no sign-up. Create an account to save.

Download the template

Want dates that adjust on their own when something slips? Open the same template in Great Gantt, no sign-up. Dates in the file start on the next business day.

WK 1
WK 2
WK 3
WK 4
WK 5
WK 6
WK 7
WK 8
WK 9
WK 10
WK 11
WK 12
WK 13
WK 14
WK 15
WK 16
WK 17
WK 18
WK 19
WK 20
WK 21
WK 22
WK 23
WK 24
WK 25
WK 26
WK 27
WK 28
Design and permits
Architectural design
Engineering designs
Permits and approvals
Budget and physical schedule
Foundation and structure
Site clearing and setup
Foundations
Foundation waterproofing
Structure and slabs
Walls and roofing
Masonry
Roofing
Building services
Electrical and plumbing
Finishing
Plaster and subfloor
Coverings and painting
Frames and fixtures
Final inspection and occupancy permit
◆ Handover
Schedule preview (calendar weeks from the start)
A TEMPLATE FOR REAL WORK

Turn Construction schedule into a real project

Start with a professional structure and customize dates, owners, and deliverables in the editor. The schedule recalculates dependencies and is ready to share with clients and your team.

  • Ready-made phases and tasks
  • Business-day dates recalculate
  • One link, always up to date
Create my project

Phases and tasks in this template

1. Design and permits

  • Architectural design10 business days
  • Engineering designs10 business days
  • Permits and approvals15 business days
  • Budget and physical schedule5 business days

2. Foundation and structure

  • Site clearing and setup5 business days
  • Foundations15 business days
  • Foundation waterproofing5 business days
  • Structure and slabs20 business days

3. Walls and roofing

  • Masonry15 business days
  • Roofing10 business days

4. Building services

  • Electrical and plumbing12 business days

5. Finishing

  • Plaster and subfloor10 business days
  • Coverings and painting15 business days
  • Frames and fixtures8 business days
  • Final inspection and occupancy permit5 business days
  • HandoverMilestone

Typical build times by type of home (rough guide)

Type of homeWorking daysApprox. months
Small single-storey timber-frame house90 to 1104 to 5
Mid-sized masonry house (this template)1396.5
Two-storey masonry house with basement170 to 2108 to 10

Includes design and permits on a five-day week. Permit backlogs, custom finishes and a wet or freezing season can add weeks to any of these.

Planning a house build with this template

Why the schedule comes before the first shovel

On a residential job, most of the expensive surprises happen in the gaps between trades. The block crew is ready but the slab has not cured. The electrician shows up for rough-in and the inspector is not booked until next week. A schedule that links each task to the one it depends on shows those gaps weeks ahead, while there is still time to move a delivery or rebook a sub.

This template is built around a masonry and reinforced concrete house, the usual method in much of Latin America, Southern Europe and the Middle East. If you are building with a timber frame, as most new homes in the US are, rename “Structure and slabs” to framing and shorten it. The logic of the sequence stays the same.

The baseline is 139 working days, including about seven weeks for design and permitting. Treat that as a starting point for a mid-sized single-family home. Your permit office, your crew size and the weather will all move it.

Phases, inspections and milestones

Each phase ends with something you can point to: an issued permit, a passed inspection, a house that is dried in. In the US those milestones usually line up with the inspections the building department requires, and in the UK with building control visits. Add them as zero-day milestones so nobody forgets to book them. The numbers below are the template's default durations in working days.

  • Design and permits: architectural design (10), engineering designs (10), permits and approvals (15), plus the budget and physical schedule (5), which runs while the permit is under review.
  • Foundation and structure: site clearing and setup (5), foundations (15), foundation waterproofing (5), structure and slabs (20). The footing inspection comes before the pour.
  • Walls and roofing: masonry (15) and roofing (10). Once the roof is on, the house is dried in and interior trades can work in any weather.
  • Building services: electrical and plumbing (12), starting as soon as the structure is up and running alongside the masonry. Rough-in gets inspected before anything is covered.
  • Finishing: plaster and subfloor (10), coverings and painting (15), frames and fixtures (8), final inspection and occupancy permit (5), then handover.

Setting it up for your project, step by step

Work through the template in this order. Fixing the outside constraints first saves rework later.

  • Check your local permit office for current review times and replace the 15-day permit task with that figure. Plan-check backlogs of several weeks are common in busy cities.
  • Set the working calendar: public or bank holidays, your crew's days off and any planned shutdown, such as the week between Christmas and New Year.
  • Ask each sub for a duration and a lead time. Windows, doors, cabinets and HVAC equipment can take six to twelve weeks to arrive, so order dates belong in the schedule too.
  • Add inspection milestones after foundations, after rough-in and before handover.
  • Assign an owner to every task, from the site supervisor to the roofer to the window supplier.
  • Share a PDF with the client and the lender, then update percent complete every week once work starts.

Who this template is for

Owner-builders running their own subcontractors. Without a general contractor, the schedule is the only thing tying the trades together. Linked tasks show which sub you need to call next and when.

Small contractors pricing a job. A clear timeline attached to a bid shows the client you have thought about sequencing. It also gives you a reference point when change orders start stretching the dates.

Borrowers on a construction loan. Lenders release money in draws as stages are completed and inspected. A schedule whose milestones match the draw stages (foundation, structure, dried in, completion) makes each draw request easier to back up.

Where house builds usually run late

Delays on residential projects tend to come from the same handful of places. Most of them can be spotted on the Gantt chart long before they hit the site.

  • Permits and plan revisions. A missing document or a plan review comment sends drawings back and can cost weeks.
  • Weather on open-ground work. Excavation, foundations and concrete pours stop in heavy rain or freezing temperatures. Many builders pad these tasks by 10 to 20 percent when they fall in a wet or cold season.
  • Concrete curing. Slabs need time before they carry load. Stripping formwork early to gain a few days is a safety problem.
  • Long-lead items ordered too late. If windows are ordered when finishing starts, the house sits waiting for them.
  • Inspections requested at the last minute. In busy areas the next slot may be days away, so book as soon as the date is firm.
  • Change orders. Moving a wall or upgrading a finish halfway through ripples into every task after it. Re-run the schedule before agreeing to the change.

Frequently asked questions

How long does it take to build a house from permit to handover?

For a mid-sized home this template comes to 139 working days, about six and a half months on a five-day week, and that already includes design and the permit. A small single-storey home can come in closer to five months, while larger or custom homes often take nine months or more. These are rough guides. Permit review times and weather vary a lot from one area to the next.

What is on the critical path of a residential construction schedule?

In this template the critical path runs through architectural and engineering design, the permit, site clearing, foundations, structure, masonry, roofing and every finishing task up to the final inspection. The budget, foundation waterproofing and the electrical and plumbing rough-in have some slack. A one-week slip on a critical task moves handover by one week.

How do I add weather days to a construction schedule?

Look at which tasks fall in your wet or freezing months, usually foundations, concrete work and roofing, and lengthen those rather than adding a lump of contingency at the end. That way the chart shows where the risk sits. Mark public holidays and site shutdowns as non-working days so the dates stay honest.

What should a construction schedule for a lender include?

Lenders mainly want to see that the stages match the draw schedule and that the completion date is realistic. Show the main phases, the inspections that trigger each draw and the handover date. You can export the Gantt chart as a PDF or Excel file and attach it to the loan application. Exports are included in the free plan.

Can I use this construction schedule for a timber-frame house?

Yes. Rename the structure task to framing and shorten it, swap plaster for drywall, and drop foundation waterproofing if you are building on a slab with no basement. Keep the links between framing and roofing and between rough-in and wall finishes, because that order does not change with the building method.

See also:Apartment renovation scheduleGantt chart or spreadsheet: when to use each

Other templates