Apartment renovation schedule for condos, co-ops and flats

Renovating a unit in a shared building means working around the board, the super, quiet hours and the freight elevator. This template lays out a full gut renovation as 13 tasks over 65 working days, about 13 weeks, from the first walkthrough to handover. Use it to set a realistic move-in date before you sign with a contractor.

65 business days13 tasks3 phases
Open the template, no sign-upSave to my account Free, no sign-up. Create an account to save.

Download the template

Want dates that adjust on their own when something slips? Open the same template in Great Gantt, no sign-up. Dates in the file start on the next business day.

WK 1
WK 2
WK 3
WK 4
WK 5
WK 6
WK 7
WK 8
WK 9
WK 10
WK 11
WK 12
WK 13
Planning and purchasing
Site survey and brief
Design and detailed budget
Building management approval
Purchase long-lead materials
Core construction
Property protection and demolition
Masonry and preparation
Electrical and plumbing work
Waterproofing and tests
Finishes
Flooring and wall coverings
Drywall and painting
Cabinetry and countertops
Fixtures, fittings and lighting
Cleaning, inspection and handover
Schedule preview (calendar weeks from the start)
A TEMPLATE FOR REAL WORK

Turn Apartment renovation schedule into a real project

Start with a professional structure and customize dates, owners, and deliverables in the editor. The schedule recalculates dependencies and is ready to share with clients and your team.

  • Ready-made phases and tasks
  • Business-day dates recalculate
  • One link, always up to date
Create my project

Phases and tasks in this template

1. Planning and purchasing

  • Site survey and brief3 business days
  • Design and detailed budget7 business days
  • Building management approval5 business days
  • Purchase long-lead materials10 business days

2. Core construction

  • Property protection and demolition5 business days
  • Masonry and preparation6 business days
  • Electrical and plumbing work8 business days
  • Waterproofing and tests4 business days

3. Finishes

  • Flooring and wall coverings8 business days
  • Drywall and painting7 business days
  • Cabinetry and countertops6 business days
  • Fixtures, fittings and lighting4 business days
  • Cleaning, inspection and handover2 business days

Typical apartment renovation timelines (rough guide)

Working time once the job is approved. Building approval comes on top and can take anywhere from a week to two months.

ScopeTypical working timeWhat usually drives it
Cosmetic refresh: paint and floors2 to 4 weeksFloor prep and drying times
Bathroom remodel3 to 6 weeksPlumbing rough-in, inspection, tile
Kitchen remodel with custom cabinets6 to 10 weeksCabinet and countertop lead times
Full gut, 1 to 2 bedrooms (this template)About 13 weeksDemo, rough-in and every finish
Co-op or condo board review1 to 8 weeksAlteration agreement and plan review

These are general ranges, not quotes. Your building's rules, permit office, contractor availability and what turns up behind the walls will move them.

Planning a renovation when you share walls with neighbors

Why a condo renovation runs on the building's clock

In a house, the contractor can start at 7 a.m. and leave a dumpster in the driveway. In an apartment building, the rules belong to someone else. Most co-op boards, condo associations and HOAs restrict noisy work to weekdays, often something like 9 a.m. to 5 p.m., ban it on weekends and holidays, and want the freight elevator booked and padded for every delivery. Some buildings in New York and other big cities also limit renovations to a set number of months and charge fees if you run over.

That is why the paperwork sits at the front of this template. Before anyone swings a hammer, the board or managing agent usually wants plans, a licensed contractor, a certificate of insurance naming the building, and sometimes a signed alteration agreement. In the UK, a leaseholder typically needs a licence to alter from the freeholder. In Canada and Australia, strata corporations have their own bylaws and forms.

Three common renovation scenarios

You just closed on a condo and want to renovate before moving in. This is the full template. The unit is empty, the crew can work every allowed hour, and the pressure comes from paying rent and a mortgage at the same time. Watch the critical path from week one.

You live in the unit and remodel one room at a time. A bathroom-first, kitchen-later plan keeps the home livable but stretches the calendar. Duplicate the core construction and finishes tasks for each room so each phase has its own dates.

You own a rental and refresh it between tenants. Here the scope is usually paint, floors and fixtures, and the deadline is the next lease start. Delete demolition and masonry, shorten the rest, and work back from the move-in date.

Paperwork to line up before demo day

The template gives building management approval 5 working days, starting right after design and budget. In practice, start the conversation with the managing agent while the design is still in progress so the review does not stall demolition.

  • Alteration agreement or HOA architectural review application
  • Certificate of insurance listing the building and managing agent
  • Building permit for electrical, plumbing or wall changes, plus a rough-in inspection
  • Contractor license number and a written scope with payment milestones
  • Freight elevator reservations and corridor protection
  • Debris plan: chute, bags or a permitted dumpster on the street
  • Notice to neighbors with the noisy weeks marked

Who you will be coordinating

A typical apartment gut job involves a general contractor, an architect or designer for drawings the board will accept, a licensed electrician and plumber for rough-in, a tile setter, a painter, a cabinet maker or millwork shop and a countertop fabricator who templates after the cabinets go in. On the building side you deal with the super for access and the property manager for approvals.

Assign each task to the person who owns it. In Great Gantt the per-person view shows what the plumber or the cabinet shop has coming up, which makes the weekly call with the contractor much shorter.

Mistakes that stretch a renovation

Ordering cabinets late is the big one. Custom or semi-custom cabinets often take 6 to 10 weeks to arrive, longer than the template's 10-day purchasing window. Place the order as soon as the design is final and add a delivery milestone. Countertops add another 1 to 2 weeks after templating.

Other common delays: closing walls before the rough-in inspection, skipping the shower pan flood test, choosing tile that is backordered, and forgetting that many buildings freeze work in late December. Older buildings also hide surprises like cast-iron drain lines or ungrounded wiring, so leave some slack after demolition.

Reading the 65 working days in this template

Planning takes 15 working days before demolition, core construction 23 and finishes 27. Long-lead purchasing runs in parallel with 18 days of slack before it would hold up flooring. Set non-working days to match your building rules, add US or UK public holidays, and save a baseline before demo. When the board asks for a timeline, export it as a PDF.

Frequently asked questions

How long does a full apartment renovation take?

As a rough guide, a full gut renovation of a one or two-bedroom apartment takes about three to four months of work, plus whatever time the board needs to approve plans. This template adds up to 65 working days, about 13 weeks, from site survey to handover.

Do I need a permit to renovate my apartment or condo?

Cosmetic work like paint and flooring usually does not need one. Moving walls, adding circuits or relocating plumbing usually does, along with inspections before walls are closed. Rules vary by city, so check with your local building department and your building management.

What does a co-op or condo board need before a renovation starts?

Most boards ask for drawings, the contractor's license and insurance certificate, a work schedule and a signed alteration agreement. Some also require a refundable deposit. The schedule from this template is a simple way to show the board when the noisy weeks will be.

What are typical quiet hours for apartment renovation work?

Many buildings allow noisy work on weekdays, often between 8 or 9 a.m. and 5 p.m., and ban it on weekends and holidays. Your house rules are the final word. Mark the restricted days as non-working in the calendar so the renovation dates stay honest.

Can I live in my apartment during the renovation?

It is possible if the work is phased by room and one bathroom always works. During demolition and drywall sanding, dust usually makes the unit hard to live in for a few days. Plan those weeks in the schedule and arrange somewhere else to stay.

When should I order cabinets for an apartment renovation?

As soon as the design and budget are signed off. Lead times of 6 to 10 weeks are common for custom work, which is longer than demolition and rough-in combined. Add a cabinet delivery milestone and link the installation to it.