Software development schedule template for client and in-house builds

Whether you are drafting the timeline section of a statement of work or planning your engineering team's next quarter, this template gives you a realistic first pass. It runs from requirements gathering through architecture, three two-week sprints, QA, user acceptance testing and production deployment. Thirteen tasks, 72 business days, with dependencies already wired up.

72 business days13 tasks3 phases
Open the template, no sign-upSave to my account Free, no sign-up. Create an account to save.

Download the template

Want dates that adjust on their own when something slips? Open the same template in Great Gantt, no sign-up. Dates in the file start on the next business day.

WK 1
WK 2
WK 3
WK 4
WK 5
WK 6
WK 7
WK 8
WK 9
WK 10
WK 11
WK 12
WK 13
WK 14
WK 15
Discovery and architecture
Goals, users and requirements
Backlog and acceptance criteria
Architecture and environments
Experience and build
Flows, wireframes and prototype
Interface design
Sprint 1 — foundations and authentication
Sprint 2 — core features
Sprint 3 — integrations and polish
Quality and release
Functional and security testing
User acceptance testing
Fixes and deployment preparation
◆ Production deployment
Post-release monitoring
Schedule preview (calendar weeks from the start)
A TEMPLATE FOR REAL WORK

Turn Software development schedule into a real project

Start with a professional structure and customize dates, owners, and deliverables in the editor. The schedule recalculates dependencies and is ready to share with clients and your team.

  • Ready-made phases and tasks
  • Business-day dates recalculate
  • One link, always up to date
Create my project

Phases and tasks in this template

1. Discovery and architecture

  • Goals, users and requirements5 business days
  • Backlog and acceptance criteria4 business days
  • Architecture and environments5 business days

2. Experience and build

  • Flows, wireframes and prototype7 business days
  • Interface design6 business days
  • Sprint 1 — foundations and authentication10 business days
  • Sprint 2 — core features10 business days
  • Sprint 3 — integrations and polish10 business days

3. Quality and release

  • Functional and security testing6 business days
  • User acceptance testing5 business days
  • Fixes and deployment preparation4 business days
  • Production deploymentMilestone
  • Post-release monitoring5 business days

Typical timelines by project size

Rough ranges for a team of three to eight people working in two-week sprints. Use them as a sanity check against your own backlog estimate.

ProjectBuild sprintsTypical end-to-end duration
Internal tool or small web app (CRUD, reports, one user role)2 to 33 to 4 months (this template: 72 business days)
Custom web platform with third-party integrations (Stripe, Salesforce, SSO)4 to 85 to 8 months
Mobile app plus admin dashboard and API6 to 106 to 10 months
Regulated or enterprise system (SOC 2, HIPAA, multiple modules)10 or more9 to 18 months

General guidance only. App store review, security audits and procurement can add weeks that no sprint plan shows.

Planning a software project timeline that holds up

Why software timelines slip

Most software estimates are really coding estimates. They leave out the weeks spent agreeing on requirements, waiting for a design sign-off, standing up a staging environment and getting real users through acceptance testing. Those weeks still happen. They just show up later as a missed date.

This template puts them on the chart. Before Sprint 1 starts there are 22 business days of discovery, backlog writing, prototyping and interface design. The build itself is 30 business days across three sprints. QA, UAT and fixes take another 15, so production deployment lands on business day 67, followed by a week of post-release monitoring. If you are writing a fixed-fee SOW, those proportions are a useful check on any timeline that looks too short.

Where this schedule fits

It is a delivery schedule for building a system, not a go-to-market plan. Teams tend to use it in one of these settings.

  • An agency or consultancy delivering under a fixed-fee SOW with milestone payments tied to requirements sign-off, UAT sign-off and go-live.
  • An in-house engineering or IT team replacing a spreadsheet process or a legacy app, where leadership wants a date for the quarterly roadmap and PTO has to be planned around.
  • A contractor or small dev shop on a time-and-materials engagement, using the Gantt to show the client what each new request does to the release date.
  • A project in a regulated space, where security review, audit evidence and formal acceptance add steps you cannot compress.

Milestones and deliverables clients expect

On client work, each phase should end with something tangible. Listing these as milestones makes it easy to tie invoices and approvals to the schedule. The template has no separate documentation task, so many teams add one alongside Sprint 3 and QA rather than writing it after launch.

  • Signed SOW and kickoff meeting
  • Requirements sign-off (PRD or functional spec)
  • Architecture decision records and environment plan
  • Clickable prototype approved by the client
  • Sprint review demo at the end of each sprint
  • QA test report and security scan results
  • UAT sign-off
  • Runbook, API docs and release notes
  • Production go-live and warranty period

How the critical path works here

After the backlog is written, the template splits into two tracks. Architecture and environments take 5 business days. Prototype and interface design take 13. Sprint 1 waits for both, which leaves architecture with 8 days of slack. A late infrastructure decision will not move your launch date, but a late design sign-off will.

Everything from Sprint 1 onward is a single chain: three sprints, functional and security testing, UAT, fixes and deployment. That is why a sprint that runs over pushes every later date, and why adding scope mid-build is best handled by adding a sprint rather than squeezing QA. Great Gantt highlights this chain and recalculates dates in business days when you change a duration.

Running sprints inside a fixed timeline

Scrum and a Gantt chart answer different questions. The board tells the team what to build this week. The schedule tells the client and leadership when the system will be live and what has to happen first. Each sprint is one bar on the timeline, and the stories stay in your backlog tool.

At each sprint review, compare progress against the baseline you saved when the plan was approved. If velocity is lower than planned, the gap is visible weeks before UAT instead of the week before go-live. Export the chart to PDF for a steering meeting, or to Excel when a client's PMO wants it in their own tracker.

Frequently asked questions

How long does a custom software development project usually take?

A small internal tool or web app often takes three to four months from kickoff to go-live. This template totals 72 business days, about 14 weeks. Projects with several integrations, a mobile app or compliance requirements commonly run six months or more. A reliable estimate comes from a sized backlog, not from the first call.

How do I put a software development timeline into a statement of work?

List the phases with their durations and the deliverable that closes each one, such as requirements sign-off, UAT sign-off and go-live. State the client's responsibilities too, like how many days they have to review and accept. Adjust the template to your scope and export it to PDF as an appendix to the SOW.

How long should UAT take in a software project?

This template allows 5 business days of UAT plus 4 for fixes, which suits a small system with users who are available to test. Larger systems often need two to four weeks. Agree in advance who signs off and what happens if testers are not available on time.

Can a Gantt chart work for an agile software project?

Yes, as long as it stays at the right level. Put each sprint on the chart as a fixed-length bar and keep stories in the backlog. The Gantt shows how sprints connect to discovery, QA, UAT and release, so stakeholders can see the likely delivery date move as scope changes.

Where does documentation fit in a software development schedule?

Treat it as its own task rather than something that happens after launch. A common setup is to run user guides, API documentation and the runbook in parallel with the last sprint and QA, so they are ready for UAT and handover.

See also:Online booking featureProduct launchGantt chart or spreadsheet: when to use each